GLASS MANUFACTURING

Medium-Voltage Backup Power Modernization for Glass Manufacturing

Brownfield modernization of a 13.8 kV backup power system with automated generator synchronization, SCADA integration and control upgrades.

LocationCuautla, Mexico
ApplicationsBackup Power · Generator Synchronization · Brownfield Modernization

Project Overview

A glass manufacturing plant in Cuautla, Mexico, needed to upgrade its existing 13.8 kV backup power infrastructure. The legacy system relied on obsolete controls that required manual operation, causing extended downtime during utility outages which directly impacted continuous melting furnaces and thermal processes.

Orange Power Systems was selected to engineer and integrate a complete control system modernization (retrofit) without replacing the expensive medium-voltage switchgear, minimizing both capital investment and plant downtime.

Installation Context

System Overview

FeatureDetail
LocationCuautla, Mexico
IndustryGlass manufacturing
ApplicationBrownfield modernization, MV synchronization
Voltage13.8 kV (Medium Voltage)
Backup generation2 × 2,000 kW (13.8 kV)
Utility connection1 × 13.8 kV Incomer
Project typeTurnkey control system retrofit

The Challenge

Glass manufacturing requires strict temperature control. Prolonged power outages not only halt production but can cause catastrophic equipment damage if molten glass solidifies within the processing equipment.

The challenge involved:

  • Replacing obsolete mechanical relay logic with modern automation
  • Implementing automatic synchronization and closed-transition with the utility grid
  • Avoiding the replacement of the existing medium-voltage switchgear and power cabling
  • Executing the complete modernization during very short maintenance windows
  • Providing operators with a modern SCADA interface for monitoring and control

The Solution

Instead of proposing new power equipment, Orange Power Systems engineered a controls upgrade package that integrated directly into the existing medium-voltage cubicles.

The solution included:

  • Master synchronization controllers integrated into the existing switchgear
  • Upgraded control systems for the two 2,000 kW diesel generators
  • Local HMI interfaces installed on the switchgear doors
  • Plant-based SCADA integration for remote operation
  • Rewiring of control circuits while keeping the medium-voltage buses intact
Engineering and Integration

How the System Operates

The modernized system operates entirely automatically. During a utility failure, the control system starts the two 13.8 kV generators, synchronizes them together on a parallel bus, and safely feeds the critical plant load.

When utility power returns, the control system synchronizes the generator bus with the utility grid, performs a closed-transition transfer without power interruption (bumpless transfer), and seamlessly unloads and shuts down the generators to return to normal standby state.

Scope of Work

  • Reverse engineering of the existing system
  • Control and instrumentation design
  • Fabrication of automation panels and retrofit doors
  • On-site mechanical and electrical installation
  • PLC and HMI software development
  • SCADA monitoring system
  • Medium-voltage commissioning and synchronization

Results

  • Guaranteed continuity — Automatic transitions ensure thermal processes and glass melting remain stable during utility events.
  • Capital savings (CAPEX) — The retrofit approach saved significant capital compared to replacing the 13.8 kV switchgear entirely.
  • Minimal downtime — The project was phased during scheduled plant shutdowns to avoid impacting production.
  • Modern operation — Operators now have full plant visibility through a state-of-the-art SCADA platform.
Finished System and Commissioning

Related Solutions

Planning a similar project?

Talk to our engineering team about your power requirements and operating challenges.